About Associated Engineering Consultants. Services we provide. Projects handled by us. Our Esteemed Clients. Our Contact.
Projects > Industrial Projects > Agrowaste Based Industries > Particle Board Plant at Basmatnaga, Dist. Parbhani

Particle Board Plant at Basmatnaga, Dist. Parbhani

Project in brief : The plant has been set up on 20 acres of land at MIDC, Basmatnagar in Maharashtra state. The main plant building (2304sqm), which houses the main process machines like matforming, hydraulic hot press, trimming and sizing machine, sander, veneering machine etc. is 96m in length, 24m in width and 5.5m in height. The 24m span structural steel roof trusses, to supporting AC sheet roofing, are mounted on RCC columns. The trusses are generally spaced at 6m c/c; except for in one bay where, the long hood of hot press penetrates the roof, the spacing is 12m.

Adjoining the main plant building is the utility block , 84m long X 6m wide X 4m high. The entire block is in RCC and houses all the utilities like compressors, hydraulic power pack, electrical control room, engineering workshop and store etc. Glue kitchen, glue storage and management room also form part of utility block. The package chiller unit, cooling tower, fans and blowers, water storage tanks etc. are mounted over the utility block slab. Next to utility block are two nos. RCC silos, 4m dia. X 8m height, for storage of core and surface chips.

Apart from above, structures like boiler house (thermic fluid heating system), chipper house and screen house which also form part of plant buildings, are situated on the rear side of main plant and utility block. In between chipper house and the screen house is wet chip silo, 7m in dia. and 11m in height. The switchyard , substation building , MCC and MDB rooms are located close to the screen house. Ground service reservoir is in the extreme north east corner of the plot.

Among the non-plant buildings are admin. building (200sqm.), essential staff quarters (150sqm), security office, toilet block etc. Next to security office is weigh bride and its cabin.

Machine foundations which constitute the major part of civil work include foundations for hammer chipper, beating flaker, dryer, boiler, chimney, compressor, matforming machine, hydraulic hot press, sander, chain and belt conveyors, blower fans, cyclones, pumps etc.

Client : Indo-Pacific Engineering Pvt. Ltd.
Project Cost : Rs. 1.75 Crores
Services Rendred : Architectural, Structural & Project Management


Back